If you’re buying a San Diego condo, ask for the association’s balcony and elevated-structure inspection report, usually first due January 1, 2025, and proof of finished repairs. Inspections repeat at least every nine years; in newer buildings, the first is due within six years of the certificate of occupancy. SB 410’s changes to those records took effect January 1, 2026.
Start with three questions. Can you use the home and its outdoor areas the way you expect? Are the remaining work and its funding clear enough to judge the purchase? Has your lender seen the records? Those answers tell you what has to be settled before you commit to an offer or head toward closing.
This guide is about following repair findings through the records. For the wider review of budgets, insurance, disclosures and the other association issues, start with the San Diego condo HOA due-diligence checklist.
Start with the complete report and the locations it covers
The condo inspection law usually called SB 326 is California Civil Code section 5551. It covers qualifying wood-supported exterior elevated elements, such as balconies, decks, stairs and walkways, in buildings with three or more attached dwelling units, where the association is responsible for maintenance or repair. The inspection looks at a sample, inspected by a licensed structural or civil engineer or architect. California Civil Code section 5551.
State law set the first inspection deadline at January 1, 2025, with another inspection at least every nine years after that. For buildings whose permit application was submitted on or after January 1, 2020, the first inspection is due no later than six years after the certificate of occupancy is issued.
Ask for the complete report, including its list of locations, the photographs, the appendices and any later supplements. Find the entries for your building, your balcony, your stairs and any shared walkway you would use. If the report numbers things in a way you cannot follow, ask for the map or key that ties it to the property address.
Current law requires the first page of the report to show the inspection date; the number of units in the project, the number of units with exterior elevated elements, the total number of elements and the number inspected; any immediate-threat findings and the number of units affected as of the inspection; and the inspector’s certification about the sample. These requirements took effect in 2026. Read an older report in light of its date; it was not necessarily required to use today’s format when it was written. SB 410, chaptered amendments, section 5.
Use those counts to see how far the report reaches. One unit may have several elements, and the inspected-element count tells you the size of the sample. Ask the inspector how the findings and any recommended follow-up apply to the location you are looking at. You should not have to guess from a photo of a similar balcony on the other side of the development.
For sales covered by Civil Code section 4525, the documents the seller must provide now include the most recent section 5551 inspection report. Ask for it early enough to chase the follow-up records through the seller and the association. California Civil Code section 4525(a)(11).
Follow each finding through the repair records
Make one short row for each finding that affects the unit or the shared areas you would use. Keep the same building and element reference as you move from document to document. The goal is to answer a specific question, such as whether the repair recommended for balcony B-4 was done, not to collect a fat folder of loosely related paperwork.
| Record | What to match | The question it should help answer |
|---|---|---|
| Inspection report and supplements | Building, element reference, finding and recommendation | What needed attention, and where? |
| Repair specification or professional clarification | The same finding and location | What work was recommended, including any further investigation? |
| Signed contract and approved changes | Locations, scope, exclusions and later additions | Does the contracted work cover that recommendation? |
| Funding and assessment records | Approved amount, money on hand and the unit’s share | How is the work being paid for, and what is still unsettled? |
| Contractor completion records | Work performed, dates and outstanding items | What does the contractor say is finished? |
| Professional follow-up and permit records, where they apply | Original finding, completed scope and required inspections | What review backs up the claim that it is finished? |
| Access notices and agency clearance, where required | The affected element and current restrictions | Can residents use it, and who authorized reopening? |
Treat this as a starting list of what to ask for. The records you need depend on the finding, the work and the local requirements that apply. Ask the professional in charge or the local agency which inspection and completion documents apply to that particular repair.
A good follow-up is precise: “Please identify the document and page that address finding B-4.” If the answer points to a later supplement, keep that supplement with the original report. If the repair changed after work began, ask how the approved change deals with the original recommendation and anything new that was found.
A hypothetical mismatch worth resolving
Suppose an inspection report recommends a waterproofing repair at balcony B-4. The association hands over a paid invoice labeled “balcony repairs,” but the attached scope lists B-1 through B-3.
The next request is for the record that ties B-4 to finished work, or a written explanation of where B-4 stands. A revised scope, another invoice and a professional follow-up may fill the gap. The original inspector or another qualified professional may need to explain how the recommendation was dealt with.
This is a hypothetical document mismatch, not a finding about any real building. The lesson is simple: keep following the same location until the records explain what happened to it. Talk about repairs elsewhere in the project does not answer the question about B-4.
Checking Chula Vista permit and inspection records
For a Chula Vista condo, open the City's Citizen Access portal and choose Building, then Search Applications. Search by address, Assessor's Parcel Number (APN) or permit number, one of them per search, and set the date range to cover the repair period. The City's online records cover permits issued since 1992.
Match each permit to the same building and repair in the association's records. Read the inspection results and dates, including the final inspection, and ask for the City's final approval record for that work. Keep it with the matching finding from the inspection report.
For records you can't find online, follow the City's instructions for researching building records. Give the address, APN, development or project name and the documents you need, such as the permit, inspection history and final approval, plus the permit number if you have it.
Check what “complete” means for access to the property
Read the report’s urgency language before you worry about a contractor’s schedule. When an inspector identifies an immediate threat under section 5551, the association must take preventive measures immediately, including restricting access to the affected element until the repairs have been inspected and approved by the local enforcement agency. In that situation, get the agency’s inspection and approval record. California Civil Code section 5551(g).
Other recommendations may call for maintenance, more investigation or planned repairs. Ask the inspector to explain anything unclear about how urgent a finding is or what order the work should go in. Do not turn a technical finding into your own conclusion about safety.
For each restriction, pin down the location, the current notice and what it takes to lift it. Then think about how the restriction would affect your day-to-day use of the home: getting onto the balcony, a shared path to the unit, or construction crews coming through occupied areas. Ask about work hours, access arrangements and anything in the schedule that depends on something else.
The final record should also list any work still left. A project can have one phase finished while other recommendations stay open. Keep those separate so that “phase one complete” does not quietly come to describe every repair in the report.
Connect the remaining work to your purchase budget and loan
Once the scope is clear, compare the repair budget with the latest approved contract and change orders. Ask whether the number being discussed is an early estimate, an accepted price or an updated total. If investigation is still open, ask how the association plans to handle additional work and when it expects a firmer cost.
Read the unit’s assessment information next to the project’s funding records. You want to know what is already due, what has been approved to be paid later and what is still only under discussion. For the detailed purchase and seller-payoff questions, use the guide to buying a condo with a special assessment. The reserve-study guide explains how to compare the wider funding plan with the association’s finances.
Give your lender the report and the follow-up records early. Under Fannie Mae’s project standards, unaddressed critical repairs can make a project ineligible. A structural or mechanical inspection completed within three years of the lender’s project review must be reviewed, and the resolution of any critical repair needs supporting documentation. The Selling Guide separates routine work from critical repairs; your lender has to apply the requirements for the loan you intend to use. Fannie Mae Selling Guide B4-2.1-03.
For the seller’s side of that issue, see our guide to selling a condo with unfinished SB 326 repairs.
Ask the lender to name the exact condition still open, what evidence will satisfy it and when the project review can be finished. Then you are planning around a specific requirement instead of a vague assurance that the building has been looked at. The wider condo mortgage project-approval guide explains how that review fits with your own preapproval.
Send a request that can be answered document by document
After reading the report, a focused request might say:
Please provide the records addressing the inspection findings for [building and element references], including any supplements, the repair scope and approved changes, completion records, any required inspections and current access restrictions. Please identify any recommendations that remain open, their planned timing and funding, and the assessments approved for this unit. For any immediate-threat finding, please include the local enforcement agency’s repair inspection and approval record.
Fill in the references before you send it through your transaction team. When a document is unavailable or does not apply, ask for an explanation. Keep a short list of the answers still outstanding, who is responsible for each one and the contract dates they bear on.
When it is time to decide, come back to the three practical questions: how you expect to use the property, what work and cost remain, and what the lender requires. If an important answer is still open, talk through that specific issue with your broker before you take your next step under the contract. Reading the technical findings belongs with the engineer or architect; any dispute over who is legally responsible calls for legal advice on that question.
Frequently asked questions
Does an SB 326 inspection cover every balcony?
Not necessarily. Section 5551 calls for a statistically significant sample of the qualifying exterior elevated elements. Ask the inspector how the report and any follow-up apply to your building and the areas you would use.
Which records show that a recommended repair was completed?
Match the original finding and its location to the repair scope, the completion records and any professional or agency inspections that applied. Ask for an explanation when the documents point to different locations or leave part of the recommendation open.
What should I request if a balcony was closed because of an immediate threat?
Ask for the current restriction notice and the local enforcement agency’s repair inspection and approval record. In that situation, section 5551 requires access to stay restricted until the agency has inspected and approved the repairs.
Can repair findings affect the condo’s financing?
Yes. Send the inspection and follow-up records to your lender early, and ask which open findings have to be resolved or documented for the loan you intend to use.
What if the report is older than the current first-page requirements?
Read it in light of its inspection date. Ask for the full report, any supplements and an explanation of what it covers; do not assume an older report had to follow the format introduced in 2026.