Start with two questions: which jurisdiction applies, and when was the permit filed
If you’re planning a new housing development of 10 or more units in unincorporated San Diego County, check your permit application date. The County’s inclusionary housing ordinance took effect October 22, 2026, and qualifying permit applications submitted on or before that date are exempt.
A city and an unincorporated community can share a mailing address or a familiar area name. Confirm which government handles land-use approvals for the property. Then ask for the project’s permit application, the date it was submitted and where the approval stands today.
The ordinance exempts certain residential permit submissions made no later than October 22, 2026, and that includes the date itself. The type of application matters: the text names a ministerial-permit application or a discretionary-permit submission. An early conversation with the County about a project is not the submission the ordinance describes.
The ordinance’s applicability and exemption provisions also deal with expired discretionary permits that cannot be renewed. If a seller tells you a project was “approved years ago,” check that against the permit record itself.
The rule starts at 10 homes
The ordinance covers new residential and mixed-use developments, for rent or for sale, that reach its 10-home threshold. Extra density-bonus homes and accessory dwelling units inside a new development do not count toward that minimum. ADUs added to existing homes have their own exemption.
Say an owner is weighing a hypothetical 12-home development in an unincorporated area. The next step is to find out how the County counts the proposed base homes and when the qualifying permit was submitted. The owner should not assume that adding bonus homes changes the count, or that the asking price for the land proves what can be built on it.
A separate exemption covers developments where every home, including density-bonus homes but not a manager’s home, is affordable housing for households at up to 80% of area median income. The applicant also has to show the County the required regulatory agreement. The project records matter more than the word “affordable” in a sales brochure.
What a covered project has to provide
A covered project has to meet the affordable-housing requirement and file an affordable housing plan with its first approval application. The required share is figured from the project’s base homes, and it depends on whether the homes will be sold or rented and whether the project needs a General Plan amendment.
- For-sale projects consistent with the General Plan: 5% very-low-income homes, 10% low-income homes or 15% moderate-income homes.
- Rental projects consistent with the General Plan: 5% extremely-low-income homes, 5% very-low-income homes or 10% low-income homes.
- Projects requiring a General Plan amendment: 20% low-income homes.
Each income category is a set share of area median income, adjusted for household size. A lower advertised price does not tell you which category a home falls in or whether your household qualifies. Ask for the approved affordability terms and the documents that govern the home.
The set-aside provisions in the signed ordinance spell out the income levels and project categories. The ordinance’s definition of the price for an ownership home includes housing costs such as property taxes, insurance and HOA dues. When you compare homes, look at the full monthly cost, not just the price.
Why a project may pay a fee instead
The final ordinance has two separate alternatives that let a fee replace up to half, or up to all, of the affordable-housing requirement. Both are in the adopted text. The full-fee alternative has to go through an approval process.
First, the applicant has to show that building the required affordable homes on the site is impractical. The County then considers alternatives in a set order: donating land, qualifying for-sale ADUs, fees for up to half of the requirement, fees for up to all of it, and building offsite. Before the County considers an option lower on that list, the applicant has to show why the options above it are impractical.
That order matters when you are sizing up a project’s cost or the homes it will deliver. A plan to pay a fee should be backed by the approved affordable housing plan and compliance method, not by an assumption that any applicant can simply choose to pay for the whole requirement.
The two fee alternatives use rates tied to the project type and the market-rate floor area. The real calculation follows the approved project’s unit mix and the method the County approved.
There are also two different ordinance dates. The housing-program ordinance, No. 11009, takes effect October 22. The companion fee-fund ordinance, No. 11010, took effect July 24, 2026, 30 days after it was adopted. That earlier date for the fund does not replace the housing program’s October start date or its permit-application exemptions.
Before buying an affordable ownership home
Ask for the affordable housing agreement and the recorded restrictions early enough to understand them before you decide to buy. The ordinance puts affordable ownership homes under resale provisions, and its agreements bind future owners and their successors.
Before I compared one of these homes with any other option, I would want to know the allowed purchase price, how a household qualifies, the occupancy requirements and the conditions on a future sale. Get those answers from the agreement itself and from whoever administers the program. A price that fits today has to be weighed against the conditions that will apply while you own the home and when you eventually sell it.
If the home is a condo, the association’s finances, insurance and rules belong in the same review. My San Diego condo and HOA due-diligence checklist walks through those records. The project’s inclusionary-housing approval tells you nothing about the HOA questions for the individual home.
If you own the land: tie the approved plan to the sale
Before you use a proposed home count or a fee option to support a land price, pull together the permit history, the current approvals and the affordable housing plan. Pin down the base-home count, any exemption you are relying on and the compliance method the County approved. If an approval has expired, find out what is still usable.
Those records let a buyer judge the work, time and cost still ahead. They also let a seller describe the property with a documented path to development instead of a best-case guess. In a sale, I would tie the open questions to the offer’s investigation period and to the conditions that have to be met before closing.
Questions buyers and owners ask
Does this housing rule apply inside every San Diego County city?
No. The County ordinance applies in unincorporated areas. A property inside an incorporated city is outside this ordinance. Confirm which government has jurisdiction over the property before you apply the County’s project requirements to it.
What if a permit application is submitted on October 22, 2026?
The exemption covers residential developments whose ministerial-permit application or discretionary-permit submission was made no later than the ordinance’s effective date, October 22, 2026, so a submission on that date is included. Ask the County to confirm the application type and the recorded submission date. An expired discretionary permit that cannot be renewed may bring the project under the new requirements.
Can I later sell an affordable ownership home at any price?
Do not count on it. The ordinance puts affordable ownership homes under resale provisions in an affordable housing agreement, with recorded restrictions that bind future owners. Read the agreement and the resale conditions before you decide whether the home fits your plans, now and later.